Postby VAF » Mon Oct 18, 2010 3:57 pm

Hi Al Aqariya,


I called Alcudia Smir on site office , about scheduled completion on AP2.
They confimed the whole development will complete by summer 2011.

From the the posted pictures this seems to be not realistic.

Regards
VAF
 
Posts: 195
Joined: Wed Jun 04, 2008 8:52 am

Postby Al Aqariya » Mon Oct 18, 2010 4:21 pm

Hi VAF,

I Agree, not the initial plan.
Beacause V-3 the villas in front of AP-4 & 5 are not started yet,
just like the rest of the AP's at the back and the commercial area.
I don't know what they exactly told you but with finishing i think they mean the started plots e.g. AP-2/4/5&7?
YB
Al Aqariya
 
Posts: 47
Joined: Thu Jul 09, 2009 7:13 am

Postby VAF » Mon Oct 18, 2010 4:36 pm

Hi Al Aqariya,

When speaking about completion, means of course about started plots ( AP-2/4/5&7 and not AP3 ,AP9, V3,..not yet started)
From what you have seen on site , do you really think completion
on AP-2/4/5&7 seems to be realistic.


Regards

VAF
VAF
 
Posts: 195
Joined: Wed Jun 04, 2008 8:52 am

Postby Al Aqariya » Sun Oct 24, 2010 9:04 pm

Hi VAF,

Yes, in my opinion it is realistic. There is still enough time.
They already started with the interior finishing, tiles, doors, windows, wardrobes etc. in AP-4 for the 3 front blocs.
Only problem is that they have to finish 3 or 4 blocs behind me.
AP-5 & AP-7 is more progressed than AP-4. All blocs are builded and windows doors etc are fitted. so it is possible to do the landscaping tree flowers etc

For AP-2 in fact it is also more progressed because all blocs have been builded, i think.
YB
Al Aqariya
 
Posts: 47
Joined: Thu Jul 09, 2009 7:13 am

Postby VAF » Mon Oct 25, 2010 10:31 am

Al Aqariya,


Good news.

Let's hope.

Regards
VAF
 
Posts: 195
Joined: Wed Jun 04, 2008 8:52 am